New Construction · Mount Dora, FL
A ground-up lakeside residence delivered on a fixed sequence
Full general contracting from site preparation through final walkthrough: foundation, framing, standing seam metal roof, full-height glazing package, mechanical coordination and interior finishes.
- Sq ft conditioned
- 3,100Sq ft conditioned
- Site duration
- 31 wksSite duration
- Trades coordinated
- 14Trades coordinated
- Open punch items at closeout
- 0Open punch items at closeout
Timeline highlights
- 01Planning & permitting6 weeks
- 02Site work & foundation4 weeks
- 03Framing & dry-in9 weeks
- 04Finishes & closeout12 weeks